HYDROSTATIC TEST REPORT

Testing BatchTEST-0001
CustomerAdvantic Building Group
Project / LocationTexas
APEX Sales Order32953
Report NumberTest-0001
Procedure / FormAST-50-APEX-3031
Issue / RevisionISS 1 / REV 1
Procedure Date9/15/2026
Report Date9/17/2026
Process Owner
System / Loop
Batch Quantity24

Hydro Test Parameters

Test Date9/16/2026
Start Time07:40 PM
Stop Time08:40 PM
Test Pressure150 psi
Test MediumDI water
Water Temperature70 deg F
Minimum Duration1 hour
Initial PSI150
Final PSI149
Test LocationNewport, DE
Pressure Gauge ID#6
Gauge Range0-300
Calibration Due Date12/5/2026
Pump / Equipment ID20271

Manifold Hydro Results

No.Manifold IDResultRemarks
1MAN-1-010PASS
2MAN-1-011PASS
3MAN-1-012PASS
4MAN-1-022PASS
5MAN-2-011PASS
6MAN-2-012PASS
7MAN-2-013PASS
8MAN-2-014PASS
9MAN-3-002PASS
10MAN-3-004PASS
11MAN-3-006PASS
12MAN-3-008PASS
13MAN-4-009PASS
14MAN-4-010PASS
15MAN-4-015PASS
16MAN-4-044PASS
17MAN-5-007PASS
18MAN-5-009PASS
19MAN-5-010PASS
20MAN-5-012PASS
21MAN-6-001PASS
22MAN-6-004PASS
23MAN-6-005PASS
24MAN-6-006PASS
Sarah Keith
Test Performed By / Signature
9/16/2026
Date
Pat Oakes
Witness / Acceptance
9/16/2026
Date

CLEANING AND CITRIC PASSIVATION REPORT REFERENCE

Testing BatchTEST-0001
CustomerAdvantic Building Group
Project / LocationTexas
APEX Sales Order32953
Report NumberTest-0001
Report Date9/17/2026
Batch Quantity24

Vendor Report Information

Vendor / SubcontractorAllegheny Surface Technolog
Vendor Report Number50269 - 9/18/26
Vendor Report Date9/17/2026
Quantity on Vendor Report24
Supporting Document Filename
Supporting Document URL
Notes

MANs Covered by Vendor Report

1.MAN-1-010
2.MAN-1-011
3.MAN-1-012
4.MAN-1-022
5.MAN-2-011
6.MAN-2-012
7.MAN-2-013
8.MAN-2-014
9.MAN-3-002
10.MAN-3-004
11.MAN-3-006
12.MAN-3-008
13.MAN-4-009
14.MAN-4-010
15.MAN-4-015
16.MAN-4-044
17.MAN-5-007
18.MAN-5-009
19.MAN-5-010
20.MAN-5-012
21.MAN-6-001
22.MAN-6-004
23.MAN-6-005
24.MAN-6-006

The manifolds listed above are associated by APEX with the referenced subcontractor/vendor passivation report. The vendor report remains the supporting technical record.

Certified By / Signature
Date
Customer / Witness
Date