Testing BatchTEST-0002
CustomerAdvantic Building Group
Project / LocationTexas
APEX Sales Order32953
Report NumberTest-0002
Procedure / FormAST-50-APEX-3031
Issue / RevisionISS 1 / REV 1
Procedure Date9/20/2026
Report Date9/22/2026
Process Owner
System / Loop
Batch Quantity24
Hydro Test Parameters
Test Date9/20/2026
Start Time06:00 PM
Stop Time06:30 PM
Test Pressure150 psi
Test MediumDI water
Water Temperature70 deg F
Minimum Duration30 minutes
Initial PSI152
Final PSI150
Test LocationNewport, DE
Pressure Gauge ID#6
Gauge Range0-300
Calibration Due Date12/5/2026
Pump / Equipment ID20271
Manifold Hydro Results
| No. | Manifold ID | Result | Remarks |
| 1 | MAN-1-008 | PASS | |
| 2 | MAN-1-013 | PASS | |
| 3 | MAN-1-016 | PASS | |
| 4 | MAN-1-044 | PASS | |
| 5 | MAN-2-007 | PASS | |
| 6 | MAN-2-010 | PASS | |
| 7 | MAN-2-044 | PASS | |
| 8 | MAN-2-045 | PASS | |
| 9 | MAN-3-003 | PASS | |
| 10 | MAN-3-009 | PASS | |
| 11 | MAN-3-044 | PASS | |
| 12 | MAN-3-046 | PASS | |
| 13 | MAN-4-012 | PASS | |
| 14 | MAN-4-013 | PASS | |
| 15 | MAN-4-045 | PASS | |
| 16 | MAN-4-049 | PASS | |
| 17 | MAN-5-014 | PASS | |
| 18 | MAN-5-015 | PASS | |
| 19 | MAN-5-039 | PASS | |
| 20 | MAN-5-050 | PASS | |
| 21 | MAN-6-002 | PASS | |
| 22 | MAN-6-003 | PASS | |
| 23 | MAN-6-042 | PASS | |
| 24 | MAN-6-048 | PASS | |
Jeremy Teder
Test Performed By / Signature
Pat Oakes
Witness / Acceptance
Testing BatchTEST-0002
CustomerAdvantic Building Group
Project / LocationTexas
APEX Sales Order32953
Report NumberTest-0002
Report Date9/22/2026
Batch Quantity24
Vendor Report Information
Vendor / Subcontractor
Vendor Report Number
Vendor Report Date
Quantity on Vendor Report
Supporting Document Filename
Supporting Document URL
Notes
MANs Covered by Vendor Report
1.MAN-1-008
2.MAN-1-013
3.MAN-1-016
4.MAN-1-044
5.MAN-2-007
6.MAN-2-010
7.MAN-2-044
8.MAN-2-045
9.MAN-3-003
10.MAN-3-009
11.MAN-3-044
12.MAN-3-046
13.MAN-4-012
14.MAN-4-013
15.MAN-4-045
16.MAN-4-049
17.MAN-5-014
18.MAN-5-015
19.MAN-5-039
20.MAN-5-050
21.MAN-6-002
22.MAN-6-003
23.MAN-6-042
24.MAN-6-048
The manifolds listed above are associated by APEX with the referenced subcontractor/vendor passivation report. The vendor report remains the supporting technical record.